File #: 25-425    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 7/9/2025 In control: Town Council
On agenda: 8/12/2025 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving the First Amendment to the Construction Contract with JOC Construction for the Kenosha Farms Culvert Replacement
Attachments: 1. Resolution 25-140, 2. Kenosha Farms Culvert Amendment
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving the First Amendment to the Construction Contract with JOC Construction for the Kenosha Farms Culvert Replacement

 

Department

DEPARTMENT:                     Utilities

Presenter

PRESENTER(S):                     Todd Fessenden, Utilities Director

end

 

Time

TIME ESTIMATE: 0 minutes
end

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $ 80,000

Balance Available:                                                                 $ 80,075.64 with transfer

Fund:                                                                                                           Storm Drainage Operating Fund

Line Item Number:                                                                 520-75-110-605000-257520

Budget Transfer:                                                                $80,000 from 520-75-110-605000-100433

New Appropriation Required:                       No


Policy

POLICY ISSUES:

1.                     Money budgeted to complete the project.

2.                     Serves the Council’s goal of maintaining infrastructure.

3.                     A delay would result in additional deterioration and higher future costs.

 

Recommendation

STAFF RECOMMENDATION:

Approve the resolution.

Body

SUMMARY/KEY POINTS

                     Culverts need replacement before Street Maintenance Project construction this summer.

                     Street Maintenance Project contract approved by Council on May 27, 2025.

                     Initial project approved by Council on June 10, 2025

 

BACKGROUND OF SUBJECT MATTER:

On June 10, 2025, Council approved a construction contract to JOC Construction for the replacement of two culverts on Allen Avenue and Nonaham Lane in Kenosha Farms. This amendment includes removal and installation of three (3) additional culverts, 1-18’’ and 2-30”, along with related infrastructure improvements, to support long-term stormwater management for the Town of Erie and surrounding neighborhood.

 

Our goal is to complete this project before the street maintenance project begins, which will involve a mill and overlay of the roadway. If this culvert project gets delayed, we could potentially have negative impacts to the new roadway after the completion of the street maintenance project.

 

Using the Gordian Job Order Contracting program, the Town received a bid for the additional work from JOC Construction for $76,023.17.

 

The project is over the existing budget. In order to complete this project, staff asks Council for approval to transfer $80,000 to Budget Line Number 520-75-110-605000-257520 (Culvert Replacement) from (520-75-110-605000-100433) (EC2 Pond Redesign).


priorities

TOWN COUNCIL PRIORITY(S) ADDRESSED:

Attractive Community Amenities

Engaged and Diverse Community

Prosperous Economy

Well-Maintained Transportation Infrastructure

Small Town Feel

Safe and Healthy Community

Effective Governance

Environmentally Sustainable

Fiscally Responsible

 