Title: A Resolution of the Town Council of the Town of Erie Approving a First Amendment to the Construction Contract with Goodland Construction, Inc. for the Downtown Infrastructure Improvements
Sponsors: Public Works
Attachments: 1. First Amendment, 2. Resolution 26-105
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a First Amendment to the Construction Contract with Goodland Construction, Inc. for the Downtown Infrastructure Improvements

 

Department

DEPARTMENT:                     Public Works


Presenter

PRESENTER(S):                     David Pasic, Public Works Director

Wendi Palmer, Civil Engineer III
end

 

Time

TIME ESTIMATE: 0 minutes
end

For time estimate: please put 0 for Consent items.

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $23,792.50

Balance Available:                                                                 $214,987.50

Fund                                                                                                          Urban Renewal Authority

Line Item Number:                                                                800-90-872-605000-100419

New Appropriation Required:                       No


Policy

POLICY ISSUES:

The Town Council must approve amendments for contracts of this amount per the Purchasing Policy.

 

Recommendation

STAFF RECOMMENDATION:

Approve the Resolution approving the First Amendment to Construction Contract with Goodland Construction, Inc. to complete the project.

Body

SUMMARY/KEY POINTS

                     This First Amendment is required to cover the cost for actual quantities installed during construction.

 

BACKGROUND OF SUBJECT MATTER:

On Aug. 27, 2024, the Town Council approved Resolution 24-118 for a construction agreement between the Town and Goodland Construction, Inc. for the Downtown Infrastructure Improvement Project.

 

This project provided improvements to the Downtown section of Erie.

 

With the completion of the project, it was discovered that there was an error in the quantities and the project contingency of $92,796 was not adequate to cover the additional cost. The Contractor has completed the project and needs to be compensated for the work they did.

 

The project contingency was requested in the August 27, 2024 Town Council Memo, however the contingency was not included in the agreement, but was included in the approved Purchase Order for the project. This agreement includes both the additional $23,792.50 funds needed for the project and the original $92,796 contingency.

 

The URA will need to also approve the additional funds. This is scheduled for the June 23, 2026 URA Meeting.