Cost as Recommended: $ 450,623
Balance Available: $ 1,243,594
Budget Line-Item Number: 100-70-440-572110-140110
New Appropriation Required: No
POLICY ISSUES:
By awarding this contract and completing the LAWSC Roof Replacement Project the Town will meet its stated priorities related to Safe and Healthy Community, and Fiscally Responsible in spending funds appropriated for this purpose.
STAFF RECOMMENDATION:
Recommendation
Approve the Resolution authorizing the Construction Contract with B&M Roofing.
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
On May 9, 2023, the Town of Erie was hit by a severe hailstorm consisting of heavy rains and hail stones greater than 2 inches in diameter. With this storm, the roof for the Leon A. Wurl Service Center was damaged. This damage was included in the Town’s initial insurance claim with the Town’s insurance carrier (CIRSA) and the Town received payment from CIRSA to complete this repair.
On Jan. 26, 2024, Town staff requested proposals for the roof replacement using a formal bid process via bids@erieco.gov <mailto:bids@erieco.gov>. Staff then conducted a mandatory pre-bid conference on Feb. 9, 2024. The Town received four complete bids on March 8, 2024, and selected B&M Roofing as the low bidder on March 25, 2024. Town staff believe that B&M Roofing is qualified to complete this project and provides the best warranty option for the Town of Erie.
COUNCIL PRIORITY(S) ADDRESSED: