Legislation Details

File #: 24-230    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 4/22/2024 In control: Town Council
On agenda: 5/14/2024 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving a Construction Contract for the Disc Golf Course Parking Lot Paving Project with Sunland Asphalt and Construction, LLC
Attachments: 1. Resolution 24-071, 2. Construction Contract - Sunland Asphalt (Disc Golf Course Parking Lot Paving)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving a Construction Contract for the Disc Golf Course Parking Lot Paving Project with Sunland Asphalt and Construction, LLC
Body

DEPARTMENT: Parks & Recreation
Department


PRESENTER(S): Luke Bolinger, Development and Neighborhood Services Division Manager
First Name Last Name, Title

FISCAL SUMMARY:
Cost as Recommended: $132,260.68
Balance Available: $168,750
Budget Line Item Number: 220-50-810-605000-100146
New Appropriation Required: No

POLICY ISSUES:
This matter concerns budgeted expenditures and thus has minimal policy implications at this point in the process because the Council has already confirmed the priority for this project.

STAFF RECOMMENDATION:
Recommendation
Approve the Resolution on a Construction Contract with for the Disc Golf Course Parking Lot Paving Project with Sunland Asphalt and Construction, LLC.
End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:
After community and stakeholder engagement in 2019, the Parks & Recreation Department completed parking lot improvements along with the Coal Creek Disc Golf Course in 2020. During the project, the old existing lot underwent redesign and reconfiguration to maximize available parking spaces and meet ADA parking requirements. The access drive was converted from recycled asphalt to paved asphalt and striped to designate parking spaces. Paving of the main lot was postponed until all reclamation efforts for the Erie Parkway bridge project were completed and accepted.

This project will pave the remaining section of the parking lot while addressing stormwater management issues. The project will paint designated spots and install a rip rap band on the western border of the lot designed to capture and reduce surface flows from the site.

Fiscal Impact: This project was included as a capital improvement project in the 2023 budgeting process and received formal approval in the 2024 Budget, with a budget alloca...

Click here for full text