Title: A Resolution of the Town Council of the Town of Erie Approving an Amendment to the Professional Services Agreement with JR Engineering, LLC for Construction Management Services for the Zones 3 and 4 Waterline Extension - Phase 2B Improvements
Sponsors: Public Works
Attachments: 1. Resolution 24-043, 2. First Amendment
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title

A Resolution of the Town Council of the Town of Erie Approving an Amendment to the Professional Services Agreement with JR Engineering, LLC for Construction Management Services for the Zones 3 and 4 Waterline Extension - Phase 2B Improvements

Body

 

DEPARTMENT:                      Public Works   

Department

 

PRESENTER(S):                      Todd Fessenden, Public Works Director

                                                               David Pasic, Town Engineer

                                                               Wendi Palmer, Civil Engineer

First Name Last Name, Title

 

FISCAL SUMMARY:

Cost as Recommended:                                           $   4,500

Balance Available:                                                                $721,900 (Pending rollover funds with First

Supplemental)

Budget Line Item Number:                       500-70-110-605000-100228

New Appropriation Required:                       No

 

POLICY ISSUES:

None.

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to amend the Agreement.

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

On Dec. 13, 2022, the Town Board executed a professional services agreement with JR Engineering, LLC for Construction Management Services for the Zones 3 and 4 Waterline Extension - Phase 2B Improvements.

 

During the construction of the two waterlines, plan changes were needed to realign the two waterlines and additional inspection time was needed due to additional work for the Construction Contractor. Although JR Engineering, LLC tried to keep the project within the contract funds, the extra work exceeded the contract amount and JR Engineering, LLC is asking for additional funds to cover their cost.

 

Staff recommends the Town Council approve the amendment to the professional services agreement with JR Engineering, LLC to authorize the additional services that were needed to complete the project.

 

Fiscal Impact:

Original Base Contract Amount:                                                                $ 169,400

1st Amendment:                                                                                                         $    4,500

Total New Contract Amount                                                               $ 173,900

 

COUNCIL PRIORITY(S) ADDRESSED:

ü                     Prosperous Economy

ü                     Safe and Healthy Community

ü                     Effective Governance

ü                     Fiscally Responsible

 

ATTACHMENT(S):                      

1.                     Resolution 24-043

2.                     First Amendment